Critical Path Calculator Knowledge Check
Sharpen your critical path calculator skills with algorithmically generated problems. Each attempt produces unique values to test your formula knowledge.
تخطي العمليات الحسابية — استخدم الآلة الحاسبة
فتح الحاسبة1 / 10
A project has two tasks: Task A with a duration of 9 weeks and Task B with a duration of 3 weeks. Task B depends on Task A. What is the earliest finish date of the project if Task A starts on week 0?