Critical Path Calculator Knowledge Check
Sharpen your critical path calculator skills with algorithmically generated problems. Each attempt produces unique values to test your formula knowledge.
Пропуснете математиката — използвайте калкулатора
Отворете калкулатора1 / 10
A project has three tasks: Task A with a duration of 10 days, Task B with a duration of 10 days, and Task C with a duration of 1 days. Task B and Task C depend on Task A. What is the total duration of the project if Task A starts on day 0?