Kanban Board Calculator Knowledge Check
Sharpen your kanban board calculator skills with algorithmically generated problems. Each attempt produces unique values to test your formula knowledge.
Пропуснете математиката — използвайте калкулатора
Отворете калкулатора1 / 10
Currently, your Kanban system has an average WIP of 20 items and an average cycle time of 3.5 days. If you reduce your WIP limit to 7 items (assuming cycle time remains constant initially), what new throughput can you expect in items per day?