Critical Path Calculator Knowledge Check
Sharpen your critical path calculator skills with algorithmically generated problems. Each attempt produces unique values to test your formula knowledge.
Spring matematikken over — brug lommeregneren
Åbn Lommeregner1 / 10
A project has two tasks: Task A with a duration of 4 days and Task B with a duration of 1 days. Task B depends on Task A. What is the total duration of the project if Task A starts on day 3?