So berechnen Sie O E E
learn.whatIsHeading
Overall Equipment Effectiveness measures equipment performance combining availability, performance, and quality. Identifies improvement opportunities.
Formel
Availability = actual run time ÷ planned run time
Schritt-für-Schritt-Anleitung
- 1Availability = actual run time ÷ planned run time
- 2Performance = actual output ÷ theoretical output
- 3Quality = good units ÷ total units
- 4OEE = Availability × Performance × Quality
Gelöste Beispiele
Eingabe
80% avail, 95% perf
Ergebnis
72.2% OEE
Häufige Fehler vermeiden
- ✕Not including planned downtime in availability calculation
- ✕Using unrealistic theoretical maximums
Häufig gestellte Fragen
What's good OEE?
Below 65% poor, 65-85% acceptable, 85%+ excellent; world-class manufacturers achieve 90%+.
What causes low OEE?
Equipment downtime, slow running speed, defects; typically 40% availability, 5% performance, 5% quality loss.
Bereit zur Berechnung? Probieren Sie den kostenlosen O E E-Rechner aus
Probieren Sie es selbst aus →