Critical Path Calculator Knowledge Check
Sharpen your critical path calculator skills with algorithmically generated problems. Each attempt produces unique values to test your formula knowledge.
Évitez les calculs - utilisez la calculatrice
Ouvrir la calculatrice1 / 10
A project has two tasks: Task A with a duration of 6 days and Task B with a duration of 2 days. Task B starts 0 days after Task A is completed. What is the total duration of the project?