Critical Path Calculator Knowledge Check

Sharpen your critical path calculator skills with algorithmically generated problems. Each attempt produces unique values to test your formula knowledge.

Évitez les calculs - utilisez la calculatrice

Ouvrir la calculatrice
1 / 10

A project has two tasks: Task A with a duration of 6 days and Task B with a duration of 2 days. Task B starts 0 days after Task A is completed. What is the total duration of the project?