Critical Path Calculator Knowledge Check
Sharpen your critical path calculator skills with algorithmically generated problems. Each attempt produces unique values to test your formula knowledge.
Hagyja ki a matematikát — használja a számológépet
Számológép megnyitása1 / 10
A project has three tasks: Task A with a duration of 1 months, Task B with a duration of 1 months, and Task C with a duration of 9 months. Task B depends on Task A, and Task C depends on Task B. What is the total duration of the project in weeks?