Petunjuk Langkah demi Langkah
Gather Your Inputs
First, identify the Planned Value (PV), Earned Value (EV), and Actual Cost (AC) for your project. These values are crucial for the calculations. Ensure they are accurate and up-to-date.
Calculate the Schedule Performance Index (SPI)
Using the formula SPI = EV / PV, calculate the project's schedule performance. For example, if EV = $100,000 and PV = $120,000, then SPI = 100,000 / 120,000 = 0.833. This means the project is behind schedule.
Calculate the Cost Performance Index (CPI)
Using the formula CPI = EV / AC, calculate the project's cost performance. For instance, if EV = $100,000 and AC = $90,000, then CPI = 100,000 / 90,000 = 1.111. This indicates the project is under budget.
Calculate the Estimate at Completion (EAC)
Apply the formula EAC = AC + (PV - EV) / CPI to estimate the total cost at completion. Continuing with our example, if AC = $90,000, PV = $120,000, EV = $100,000, and CPI = 1.111, then EAC = 90,000 + (120,000 - 100,000) / 1.111 = 90,000 + 20,000 / 1.111 = 90,000 + 18,002 = $108,002.
Interpret Your Results
With your SPI, CPI, and EAC calculated, you can now interpret the results. An SPI < 1 indicates the project is behind schedule, while an SPI > 1 means it's ahead of schedule. A CPI < 1 shows the project is over budget, and a CPI > 1 indicates it's under budget. The EAC provides an estimate of the total project cost at completion.
Using the Calculator for Convenience
While manual calculations are educational, using an earned value calculator can save time and reduce errors. It's especially useful for complex projects with many tasks and frequent updates. For convenience and to ensure accuracy, consider using an online earned value calculator after you understand the manual process.
Introduction to Earned Value Management
Earned Value Management (EVM) is a powerful tool used to measure project performance and progress. It combines scope, schedule, and resource measurements to assess the project's overall health. In this guide, we will walk you through the steps to calculate earned value management metrics manually.
Understanding the Metrics
Before we dive into the calculations, let's define the key metrics:
- PV (Planned Value): The total budget for the work scheduled to be completed by a specific date.
- EV (Earned Value): The value of the work actually completed by a specific date.
- AC (Actual Cost): The total cost incurred to complete the work by a specific date.
- SPI (Schedule Performance Index): Measures the project's schedule performance.
- CPI (Cost Performance Index): Measures the project's cost performance.
- EAC (Estimate at Completion): Estimates the total cost of the project at completion.
Formula
The formulas for calculating these metrics are as follows:
- SPI = EV / PV
- CPI = EV / AC
- EAC = AC + (PV - EV) / CPI