Critical Path Calculator Knowledge Check

Sharpen your critical path calculator skills with algorithmically generated problems. Each attempt produces unique values to test your formula knowledge.

Salta i calcoli: usa la calcolatrice

Apri Calcolatrice
1 / 10

A project has three tasks: Task A with a duration of 4 days, Task B with a duration of 9 days, and Task C with a duration of 8 days. Task B and Task C depend on Task A. What is the total duration of the project if Task A starts on day 0?