Test your understanding of critical path calculator with randomized questions. Each attempt generates new numbers for a fresh challenge.
गणित वगळा — कॅल्क्युलेटर वापरा
कॅल्क्युलेटर उघडा1 / 10
A project has two tasks: Task A with a duration of 1 weeks and Task B with a duration of 7 weeks. Task B depends on Task A. What is the earliest finish date of the project if Task A starts on week 0?