Calculates the maximum time allowed per unit to meet production targets. Sets the pace for production planning.

Formule

Formula: takt time = available time ÷ target units

Stapsgewijze handleiding

  1. 1Available production time per day (minutes)
  2. 2Daily production target (units)
  3. 3Formula: takt time = available time ÷ target units
  4. 4One unit must complete in less than takt time

Uitgewerkte voorbeelden

Invoer
480min/day, 100u
Resultaat
4.8 min/unit

Veelgemaakte fouten om te vermijden

  • Confusing takt time (pace) with cycle time (actual)
  • Not adjusting for breaks and changeovers

Veelgestelde vragen

Why is takt time important?

Provides production target pace; identifies if current speed can meet demand.

How do I reduce takt time?

Increase available time (extend hours), or reduce target (fewer units needed).