learn.howToCalculate
learn.whatIsHeading
Calculates the maximum time allowed per unit to meet production targets. Sets the pace for production planning.
Formule
Formula: takt time = available time ÷ target units
Stapsgewijze handleiding
- 1Available production time per day (minutes)
- 2Daily production target (units)
- 3Formula: takt time = available time ÷ target units
- 4One unit must complete in less than takt time
Uitgewerkte voorbeelden
Invoer
480min/day, 100u
Resultaat
4.8 min/unit
Veelgemaakte fouten om te vermijden
- ✕Confusing takt time (pace) with cycle time (actual)
- ✕Not adjusting for breaks and changeovers
Veelgestelde vragen
Why is takt time important?
Provides production target pace; identifies if current speed can meet demand.
How do I reduce takt time?
Increase available time (extend hours), or reduce target (fewer units needed).
Klaar om te berekenen? Probeer de gratis Takt Time-rekenmachine