Critical Path Calculator Knowledge Check

Sharpen your critical path calculator skills with algorithmically generated problems. Each attempt produces unique values to test your formula knowledge.

ଗଣିତକୁ ଏଡ଼ାଇ ଦିଅନ୍ତୁ - କାଲକୁଲେଟର ବ୍ୟବହାର କରନ୍ତୁ |

କାଲକୁଲେଟର ଖୋଲନ୍ତୁ |
1 / 10

A project has three tasks: Task A with a duration of 9 days, Task B with a duration of 7 days, and Task C with a duration of 0 days. Task B depends on Task A, and Task C depends on Task B. What is the total duration of the project if Task A starts on day 0?