Overall Equipment Effectiveness measures equipment performance combining availability, performance, and quality. Identifies improvement opportunities.

Wzór

Availability = actual run time ÷ planned run time

Przewodnik krok po kroku

  1. 1Availability = actual run time ÷ planned run time
  2. 2Performance = actual output ÷ theoretical output
  3. 3Quality = good units ÷ total units
  4. 4OEE = Availability × Performance × Quality

Rozwiązane przykłady

Wejście
80% avail, 95% perf
Wynik
72.2% OEE

Częste błędy do unikania

  • Not including planned downtime in availability calculation
  • Using unrealistic theoretical maximums

Często zadawane pytania

What's good OEE?

Below 65% poor, 65-85% acceptable, 85%+ excellent; world-class manufacturers achieve 90%+.

What causes low OEE?

Equipment downtime, slow running speed, defects; typically 40% availability, 5% performance, 5% quality loss.

Gotowy do obliczeń? Wypróbuj darmowy kalkulator O E E

Spróbuj sam →