Critical Path Calculator Knowledge Check

Sharpen your critical path calculator skills with algorithmically generated problems. Each attempt produces unique values to test your formula knowledge.

跳过数学——使用计算器

打开计算器
1 / 10

A project has three tasks: Task A with a duration of 4 weeks, Task B with a duration of 3 weeks, and Task C with a duration of 3 weeks. Task B and Task C depend on Task A. What is the total duration of the project if Task A starts on week 3?