Critical Path Calculator Knowledge Check

Sharpen your critical path calculator skills with algorithmically generated problems. Each attempt produces unique values to test your formula knowledge.

Praleiskite matematiką – naudokite skaičiuotuvą

Atidaryti skaičiuotuvą
1 / 10

A project has three tasks: Task A with a duration of 5 weeks, Task B with a duration of 4 weeks, and Task C with a duration of 10 weeks. Task B depends on Task A, and Task C depends on Task B. What is the total duration of the project?