Critical Path Calculator Knowledge Check
Sharpen your critical path calculator skills with algorithmically generated problems. Each attempt produces unique values to test your formula knowledge.
Preskočite matematiku — koristite kalkulator
Otvori kalkulator1 / 10
A project has three tasks: Task A with a duration of 10 days, Task B with a duration of 9 days, and Task C with a duration of 5 days. Task B depends on Task A, and Task C depends on Task B. What is the total duration of the project if Task A starts on day 5?